A sample timeline for completion of a comprehensive assessment is as follows:
| Contract awarded to The HSUS ASC program |
To be determined |
| Solicitation of public comment begins |
2 weeks following contract |
| Background documentation due to The HSUS |
4 weeks following contract |
| Solicitation of public comment ends |
6 weeks following contract |
| Team itinerary development |
6 weeks following contract |
| HSUS ASC team site visit |
8 weeks following contract |
| HSUS ASC report completed |
12 weeks following completion of site visit |
The ASC program receives numerous inquiries each year, all of which are subject to various stages of negotiation. Based on level of demand and time constraints, the timeline confirmation of any specific evaluation is not possible until a mutually agreed upon contract has been executed. Timelines for services will be established on a first-come, first-served basis, which may result in a delay of up to 90 days from the date of contract to commencement of services.
|